IDEA Hainaut invests in a new 40-hectare industrial zone in Strépy. TRBA carries out the preparatory infrastructure works. Accounting for 700,000 m³ of excavated and treated soil.

Challenge

TRBA supplies 40,000 tonnes of lime for the soil treatment on the site. Afterwards they build 33,000 m² of roads, 20,000 meters of curbs and ditches with 7600 meters of drainage and 13,000 meters of cables and piping.

 

 

Client: 
Intercommunale IDEA
Project: 

New industrial area Strépy-Zuid

Budget: 
4 960 000.00€